The Texas Water Development Board is conducting a project feasibility review of the proposed Marvin Nichols Reservoir project, pursuant to HB 1 88(R). This feasibility review shall analyze the implementation timeline, associated costs, land acquisition considerations, and economic impact of the proposed project. A report regarding the findings of this review shall be prepared and submitted by the TWDB to the Legislative Budget Board and governor no later than January 5, 2025. The TWDB is holding a public input period as part of this feasibility review. The public input period will end on December 1, 2023. Input and any supporting documentation can be emailed to feasibility@twdb.texas.gov.

Input and information are specifically requested on the following topics:

  • Implementation timeline
  • Associated costs
  • Land acquisition considerations
  • Economic impact